File photo
Key Points
- The Apopka CRA Board unanimously approved a termination agreement on Nov. 12 for the stalled Station Street redevelopment project.
- The termination agreement cites an FDEP environmental clearance denial and states that the developer is not in default, despite the city's earlier default action.
- The agreement still requires final City Commission approval and does not identify a replacement developer or new redevelopment plans.
The Apopka Community Redevelopment Agency (CRA) Board unanimously approved a mutual termination agreement Thursday, Nov. 12, for the stalled Station Street redevelopment project, moving the proposed downtown development closer to cancellation.
The agreement between the city, CRA and Standard Investments and Holdings LLC will next go before the City Commission for final approval. The project was intended to bring affordable housing, public event space and pedestrian connections to downtown Apopka.
“It’s finally moved forward, finalized, and finished,” CRA Chair Nick Nesta said as he introduced the termination agreement.
The CRA oversees efforts to revitalize downtown Apopka through redevelopment, infrastructure improvements and economic development initiatives. Its board consists of the mayor, four city commissioners and two appointed representatives, one from the city and one from Orange County.
The proposed agreement attributes the project’s delays to an environmental clearance issue involving the Florida Department of Environmental Protection (FDEP). According to the document included in the CRA agenda packet, FDEP denied Orange County’s request for a Site Rehabilitation Completion Order necessary for brownfield clearance of the property.
The agreement describes the circumstances as beyond the developer’s control and states that the developer was unable to meet the project’s anticipated schedule. It also states that the developer “is not in default of the Agreement.”
That language contrasts with the City Commission’s June 3 vote authorizing a notice of default to Standard Investments after the developer failed to submit required design specifications.
At the June meeting, then-Interim City Administrator Radley Williams said the developer had not submitted completed plans for the proposed public plaza and Downtown Apopka Trail extensions, which were due July 15, 2024.
Williams acknowledged environmental delays but said additional studies had been completed earlier in the year. City staff considered the project stalled and recommended issuing the notice, which would give the developer 30 days to address the default after receiving it.
The proposed termination agreement does not identify when FDEP denied the environmental clearance request or explain how that decision affected the developer’s previously identified failure to submit plans.
Board members did not publicly discuss the environmental issue or the developer’s default status before approving the termination Thursday.
CRA member John Drago moved to approve the agreement as presented, and member Sam Ruth seconded the motion. The board approved it unanimously after an opportunity for public comment.
“I’m disappointed, but it’s okay,” CRA Vice Chair Diane Velazquez said following the vote.
Nesta said the matter could be discussed further when the agreement comes before the City Commission.
The original development agreement, reached in 2024, contemplated up to 60 affordable housing units, a city-owned public plaza, parking and connections to the Downtown Apopka Trail.
Under the proposed termination, the development agreement would end when the last of the three parties signs the document. The city clerk would then have 14 days to record the termination in Orange County’s public records.
The termination agreement does not identify another developer or outline plans for redeveloping the property.